Description:

Emergency Refurbishment Work after Hurricane Dorian, September 2019

Client:

Nova Scotia Power

Work Completed:

At the request of the client, our teams traveled to urban and remote areas across Nova Scotia, repairing power lines and assessing the damage Dorian caused. Damage included an estimated 3,700 trees on lines and 300 broken or leaning poles. Work was prioritized to safely restore service to critical customers and infrastructure, then to the greatest number of customers as quickly as possible.

Location:

Nova Scotia

  • Project Name Emergency Refurbishment - Storm Damage
  • Client Locke's Electrical
  • Date 2017
  • Duration 3 days
  • Location Newfoundland